West Campus Sports Development - Project Update
2008-12-11
The project is now well underway and is being carried out on a phased basis from July 2007 to 2011. To date phase one of the project is nearing completion and sections of phase two have also commenced.
Phase 1 (completed*)
- 3 Sand Based Flood Lit Pitches *
- Preparation of All-Weather Pitch *
- Renovate Old Farm Buildings into workshop/storage units
Phase 2
- All-Weather Pitch (foundation is in place)
- Fencing of Site *
- Sports Pavilion (Dressing Rooms, Offices etc)
Phase 3 (work to begin in 2009 to be complete in 2011)
- Multi-Purpose Sports Hall
Phase 4 (work to begin in 2010)
- Athletics Track/Facilities
The delivery of the above within the specified time-scales will depend on the level of funding available. The entire project will be financed by Campus Services and external funding sources i.e. grants etc.